As well as the standard tests prescribed by the regulations, additional prototype tests may be carried out on request by our customers (or wherever our technical staff see fit). The aim of these tests, always developed in compliance with the current regulations, is to evaluate the product in the context of its actual use. In order to do this, we have produced equipment capable of recreating the same functional conditions that occur during common applications.
- UPS Load Simulation (Test carried out on UPS transformers).
- Load Simulation by Inductance with Presence of Harmonics (Test carried out on PFC inductors, harmonic filters and blockers, UPS, inverters and converters).
- Resistive Load (Test that can be carried out on all EMG products).
For further information, please contact our technical office.